The new sanitary sewer installed as part of this project is active and the old sewer has been filled with concrete. Most of the curb and gutter and sidewalk in the sewer reconstruction area was poured this past Wednesday. The remaining sidewalk and driveways will be poured within the next couple of days, weather permitting. Please continue to keep off the new driveways until they have had time to cure – we appreciate your patience and cooperation in this matter.
Up Next
The aggregate base in the road continues to be graded in preparation for the asphalt base course. The asphalt base course is anticipated to be paved on Northland Drive from Lewis Street to Wolverine Blvd this Friday – this date may vary with weather. After the base course is paved more extensive lawn restoration will begin.
Manhole castings have been removed along Courtland Street in preparation for milling. The top course of asphalt will be milled early next week on Northland Drive between Lewis Street and Pearl Street and on Courtland Street between Dayton Street and Monroe Street.
The last major item of construction is the paving of the top course of asphalt. The top course is anticipated to be paved over the entire project starting next Thursday.