Work completed/in progress from the last update:

  • 160th Avenue intersection closed and connection to existing 30″ interconnect in progress.
  • Leak between 160th and 152nd Avenue identified and repaired. Pressure test passed.
  • HDD pull back completed.
  • 36″ transmission main construction east of 144th progressed to Aniline Avenue.
  • Water service replacement between Aniline and Division.
  • Sanitary sewer lateral relocation as required.
  • Paved base course of asphalt between 160th and 152nd.
  • Precision Trenching continued their work to relocate and underground HBPW electric service between Aniline and Division.

 

Anticipated activities for this week and next week include:

  • Complete connection to 30″ interconnect and open 160th Ave intersection. Expected to turn water back on Monday, 6/20, and open intersection either Wed 6/22 or Thurs 6/23.
  • Mill between 160th and 152nd (south half of road for road resurfacing)
  • Mill between Aniline and River (north half of road for water main and storm sewer construction)
  • Lawn restoration between 160th and 152nd.
  • Water service and sanitary lateral verification and replacement between Aniline and River.
  • Dewatering setups as necessary.
  • Start transmission main installation east of Aniline.
  • Start transmission main installation between 152nd and Pine Creek crossing.