Progress Report

Phase II construction of the Spoonville trail is underway! Construction began on June 1 and is well into the third week already. So far, we have placed the gravel base along the golf course entrance and a good portion of the earth work is finished at the Trailhead location on 120th  Avenue.

 

What to Expect Next Week (June 22–26)

We plan to finish up the earth work at the Trailhead, and will begin the process of building the trail along Leonard Road from the Golf Course west toward 120th  Avenue.

Be mindful of trucks hauling material in and out of the trailhead at 120th Avenue. Next week Trucks will be hauling down Leonard Road using a shoulder closure.