Dean’s Excavating has revised their construction schedule to generally construct the force main from the north end to the south end. This was done in an effort to limit the impact to Rockford Public Schools by completing the work along Edgerton Avenue prior to the 2024/2025 school year starting.
Below is an UPDATED anticipated schedule for force main construction. The anticipated lift station construction schedule has not changed.
Force Main Construction:
- Saddle Ridge (Edgerton to Lift Station) – 7/8 to 8/2
- Edgerton Avenue & US-131 Crossing – 8/2 to 8/10
- Elstner Avenue – 8/11 to 8/17
- 11 Mile Road – 8/8 to 8/29
- Wolven Avenue – 8/30 to 10/9
Lift Station Construction:
- Set Wet Well & Install Gravity Sewer – 8/19 to 9/4
- Install Pumps and Electrical Work – 9/30 to 11/1
- Lift Station Start Up – 11/2 to 11/11
- Lift Station Restoration & Generator Installation – May & June 2025