Remaining Work:
- Black Gold was on site today, Tuesday, June 27, and completed the repaving of the asphalt driveways.
- K&R will be on site Thursday, June 29, and will touch up lawn restoration along the road and driveway edges prior to the July 4th holiday. K&R will restore along the edges of the new road and driveways but does not plan to redo any of the areas not impacted by the repaving work. Homeowners must continue to water the new grass to promote good grass growth. Routine grass cutting and fertilizer applications are also required to control weeds.
Please contact any project representative if you have questions or concerns.