Progress Update

Sanitary sewer installation along Francis Ave and Eastman Ave is complete and work on Britain Ave has begun. Overall progress has been slower than anticipated, due in part to deep sewer and challenging soil and groundwater issues.

 

Up Next

Sanitary sewer installation on Britain Ave will continue over the next several weeks. As sewer gets shallower, production is anticipated to increase.