THE ROAD REPAIR WORK HAS BEEN RESCHEDULED FOR NEXT WEEK due to circumstances outside of the Township’s control.
Road repairs are set to begin next week Tuesday (6/13) and are anticipated to be completed by Friday (6/16). Only Northville Drive will be repaved to correct drainage issues. At this time, Leelanau Drive will not have work completed on it.
Milling will begin on Tuesday and will be completed either that day or Wednesday morning. Paving will take place the second half of the week and it depends on when the milling work is completed, when a paving crew is available, and the weather. Select driveways which need to be replaced will not be completed until after June 19 to allow time for the new road surface to cool off.
Please contact any project representative if you have questions or concerns.