Progress Report:
The new lift station is up and running! Wastewater is no longer flowing to the old wastewater treatment plant building and it is all flowing into the new lift station. Dean’s has completed all of the pipe work associated with this project and will work on restoration around new new lift station in the next two months as weather allows.
Upcoming Work:
- The new generator will be installed next to the new lift station when it is delivered around the end of February.
- Dean’s will complete remaining concrete work around the new lift station in late February or early April once the frost is out of the ground.
- The access driveway will be paved in April.
- Dean’s will complete landscape restoration around the new lift station.