Road rebuilding continued on Jefferson and Dryden, north of Jefferson last week with the installation of curb and sidewalk . Additionally, water main was installed in State street to tie into the existing system. The focus this week will be on water main installation on Dryden, south of Jefferson, as well as, preparations for asphalt installation next week on Jefferson and Dryden, north of Jefferson.
Work Completed Last Week
- Installation of water main at State Street.
- Installation of concrete curb on Jefferson and Dryden, north of Jefferson.
- Installation of sidewalk and driveways on Hart, Jefferson, and Dryden, north of Jefferson.
Anticipated Work This Week
- Installation of sidewalk ramps on Jefferson and Dryden, north of Jefferson.
- Water main installation will begin on Dryden, south of Jefferson.
- Preparations for asphalt on Jefferson and Dryden, north of Jefferson. Asphalt installation is currently scheduled for June 5th.