Goodrich Park Parking Lot:
- Additional electrical work for new lighting
- Asphalt pavement was removed and is getting prepared for new pavement
- Additional electrical work for new lighting
- Additional electrical work for new lighting
- Asphalt pavement was removed and is getting prepared for new pavement
- Deck and railings finished on the deck
- Concrete work is finished
- Lawn area was topsoiled and hydroseeded
- No work to be done on Monday, May 27, 2024
- Waiting for old lights to be removed from Goodrich Park and Spring Street Parking Lots
- Railings at new concrete stairs near Fishing Deck
- Restriping of handicapped parking near Fishing Deck
- Additional grading for new pavement in parking lots
- If lighting work is completed in the parking lots, the paving can be completed