Work completed recently:
- Water main installation continues south of Lewis Street
- Grading and preparation of sidewalk concrete between Slocum and Sophia
- No work on Monday, May 27, 2024 due to Memorial Day Holiday
- Pour concrete curb and gutter and sidewalk between Slocum and Alice – Please allow a minimum of 3 days for the concrete to cure before driving on it
- Continue water main installation from south of Lewis to Benston
- Continue water main installation on the east side of Warner Street south of Lewis Street to Benston Street
- Restoration of areas between Slocum and Sophia