The focus this past week was on completing straight-line curb & gutter and beginning placement of intersection curb & gutter, as well as sidewalk. The focus this week will continue to be on installing the curb, sidewalks, and driveway approaches, as well as fine grading in preparation for asphalt pavement.

 

Work Completed Last Week

  • Contractor completed all straight-line curb & gutter.
  • Contractor began placing intersection curb & gutter.
  • Contractor began placing sidewalk.

 

Anticipated Work This Week

  • Continue placing sidewalk and drive approaches.
  • Continue placing curb & gutter radius at intersections.
  • Begin fine grading of aggregate grade in preparation for asphalt pavement.