This Week

Carpenter crews have finished the decks for both overlooks and the kayak/fishing platform. The railings are ordered and should be ready for installation in the spring. This week crews began work on the boardwalk, adding stringers between the piles to build the deck on.

In addition, pile crews are continuing to place piles out across the lake to NMC. Almost two-thirds of the piles are placed, and most have been proofed and ready for deck construction.

 

Next Week

Work will continue on the same tasks as this week. In addition, they will likely begin to clear the areas on Medalie Park to prepare to construct the bridge abutments. The manufacturer anticipates the two bridges will be delivered to the project in early to mid-December.