The focus this past week was on water main installation on Polk Road near the intersection of Griswold Street moving to the west. Additionally, the sanitary sewer has been tied into Grey & Company. The focus this week will continue to be on installing the remaining water main in Polk Road.
Work Completed Last Week
- The Contractor installed water main on Polk Road working west from Griswold Street.
Anticipated Work This Week
- The Contractor will continue installing water main on Polk Road.
- The Contractor will begin placing aggregate base in preparation for road building.