PAVING UPDATE:

Milbocker’s subcontractor, Black Gold, was unable to make it to the site on Saturday to pave the intersection patches but was scheduled to be on site Tuesday (10/8).

Residents in Phase 2 will notice that flags marking the existing underground utilities (sewer, water, gas) have showed up along the entire project site. This is for the tree clearing that started today along Audley and Daylor. All of the trees will be removed this week.

Proposed water main stakes were accidentally installed along Northgate between Eldon and Miramar on Monday. Water main along Northgate will not be installed until next spring.