Work Completed this Past Week

  • The new water main was connected to the existing water main system at Pinecrest, Tulgeywood and Sunset
  • Additional storm drains were installed
  • Finished installing water service lines to the new water main

 

Work Anticipated Week of September 11, 2023

  • Finish final water main connection at the north end at Benston on Monday (weather dependent)
  • Finish storm drainage system (which should complete the underground work)
  • Begin rebuilding the road with road gravel
  • Possibly finish any concrete work north of Benston

 

Work Anticipated Week of September 18, 2023

  • Continue rebuilding road with grading and delivery of road base gravel.
  • Prepare for installation of concrete curb and gutter and driveway approaches