Progress Report:
Approximately 1,100 feet of the planned 1,250 feet of sanitary sewer has been installed on Dixie Drive. Lateral services have been replaced from the mainline sewer to the property line on all but 2 properties.
Approximately 90% of the mainline water main on Dixie Drive has been installed. The tie in to the existing water main at the intersection of Empire Ave and Dixie Drive has also occurred after the new water main passed the pressure and chlorination tests.
Upcoming Work:
Sanitary sewer installation is planned for completion by the end of the week.
Water main installation is planned for completion along Dixie Drive by the end of the week, after which water service installation will begin.