Filter building construction has begun with footings and foundation. Rebar and forms are being installed for the step footings. 

Upcoming Schedule:

  • The concrete pour is scheduled for Friday, weather dependent.
  • Dredging of the lakes for the filter beds is currently scheduled to start next week.