Sanitary sewer, storm sewer, and water main installation West of Schuster Ave is complete. Work on rebuilding the road West of Schuster will begin next week. Access to Shakespeare and Schuster Ave will continue to be possible from the BL until further notice. Access to Lake Street from the West will remain closed until Lake Street is paved up to Schuster Ave.

Construction East of the BL is planned to begin next Wednesday, 4/26. This will involve milling Lake Street from I-94 BL to Lamont. Detour route phase B will go into effect at this time and will run in conjunction with phase A. Access to Lamont will remain open and be possible from the East. At no time during construction will Lamont Ave be completely closed.