Work expected the week of August 21, 2023:
- Surveying and saw-cutting at Seng, Kunz and Aue/Miller sites.
- Pavement removal at Seng.
- Water main installation on west side of Seng between Eugene and Hile.
Work Expected the week of August 28, 2023:
- Pavement removal at Kunz.
- Testing water main on Seng.
- Water main installation on west side of Kunz between Eugene and Hile.