Caledonia Township is excited to begin the next section of Shared Use Pathway with the goal of increasing walkability around Campau Lake! This connection will serve as a safe route for students to get to school while also allowing for increased safety in community recreation along the busy roads that surround Campau Lake.

CHOP Tree service has begun their removal work for the project. Once it is completed this week, they plan to begin working on the trail beginning on Whitneyville Avenue at Garbow Drive and heading north.

Brenner Excavating will finish the section on Whitneyville Avenue before moving on to 66th Street and finally McCords Avenue.

Trash and mail services should not be interrupted during the construction process, so please continue as normal with these activities and let a project representative know if you have any questions.