Contract #1 work completed since last update (12/3/2019):

  • Startup of new south activated sludge pumps
  • Several runs of yard piping
  • Painting in headworks building
  • Overhead door installed in headworks building

 

Anticipated work in January:

  • Several runs of yard piping
  • Existing grit building bypass and tie-in
  • North activated sludge piping, valving, pump installation

 

Contract #2 work completed since last update (12/3/2019):

SPRING LAKE PUMP STATION:

  • Connected station to existing force main
  • Completed installation of pumps, valves, and piping
  • Started painting equipment
  • Poured new sidewalk
  • Continued installation of electrical and controls equipment

 

Anticipated work in January:

  • Complete punch list work at Grand Haven Pump Station
  • Install all remaining equipment at Spring Lake Pump Station
  • Paint remaining equipment and building interior
  • Perform startup of pump station
  • Begin restoration