Contract #1 work completed since last update (12/3/2019):
- Startup of new south activated sludge pumps
- Several runs of yard piping
- Painting in headworks building
- Overhead door installed in headworks building
Anticipated work in January:
- Several runs of yard piping
- Existing grit building bypass and tie-in
- North activated sludge piping, valving, pump installation
Contract #2 work completed since last update (12/3/2019):
SPRING LAKE PUMP STATION:
- Connected station to existing force main
- Completed installation of pumps, valves, and piping
- Started painting equipment
- Poured new sidewalk
- Continued installation of electrical and controls equipment
Anticipated work in January:
- Complete punch list work at Grand Haven Pump Station
- Install all remaining equipment at Spring Lake Pump Station
- Paint remaining equipment and building interior
- Perform startup of pump station
- Begin restoration