Contract #1 work completed since last update (11/1/2019):

  • Concrete sidewalk, pipe bollards, awnings installed on headworks building
  • SE primary clarifier demolition and coating
  • Electrical switch-over to new transformer and automatic transfer switch
  • Metal grating and stairs in headworks building

 

Anticipated work in December:

  • Several runs of yard piping
  • South activated sludge pumps startup
  • Painting, caulking, door installation in headworks building
  • Installation of lighting and electrical equipment in headworks building

 

Contract #2 work completed since last update (11/1/2019):

GRAND HAVEN PUMP STATION:

  • Performed startup of pump station and took bypass pumps out of service

 

SPRING LAKE PUMP STATION:

  • Installed temporary pump station bypass system
  • Demolished existing equipment and began installation of new equipment
  • Excavated to prepare for connection to existing force main
  • Poured concrete bases for new pumps

 

Anticipated work in December:

  • Remove bypass system from Grand Haven Pump Station
  • Connect new piping to existing force main at Spring Lake Pump Station
  • Install all remaining equipment
  • Paint equipment and building interior
  • Perform startup of pump station