Progress Report: K&R has completed most of the mainline force main installation along HBPW Electric corridor, and has moved to installation along James Street, starting at Beeline Road and working west. Installation along James Street should be complete by early next week (February 17). Daily lane shifts for eastbound traffic continue (weather dependent) to assist in safe construction practices for workers and vehicle traffic.
Next Steps: Pump Station No. 31 site preparation for concrete work (March), and the CSX/Lakewood Blvd bore & jack operations to begin later March and extend into May.