Progress Report:
The assembled pipeline is now in place under the river as planned! The pullback operation started on Tuesday morning and progressed throughout the day until completion at approximately 7:00 Tuesday evening. This is a major milestone for the project with the trenchless work now substantially complete.
Upcoming Work:
Much work still remains to be completed on each side of the river. Directional drilling equipment will be demobilized over the next week and preparations for force main installation on the wastewater treatment plant site will begin.