The underground piping around the filter building has been installed.

Upcoming Schedule:

  • Construction of the outlet will continue, weather permitting.
  • The floor drain and sump installation will be finished in the filter building.
  • Planning to install the Crooked Pump Station wet well in the next few weeks.