Progress Report:

  • Maple St. Storm Sewer: Storm sewer catch basin installation on Maple Street between Monroe and Fremont Street is planned to be completed by the end of this week. The remaining storm laterals on Maple Street are planned to be completed by the end of this week. If the Contractor is unable to complete the laterals by the end of the day on Friday, they will plan to complete the remaining laterals on Saturday.
  • Lincoln Street: Sanitary lateral installation along Lincoln Street was completed on Monday. The water main tie-in at Bridge Street was completed on Tuesday. The old water main has since been removed. The Contractor plans to start storm sewer installation this week along Lincoln Street starting on the north end heading south.
  • Main Street: Exploratory digging for investigation of the old Main Street water main was completed this week. With new information now uncovered, a plan for completing the water main connection has been established. This work is planned for next week, and then the road and sidewalk can be restored.

 

Lead Service Line Replacements:

Make sure to see our “Lead Service Line Replacements” page for the latest status report on lead service lines for the project.