Progress Report: Concrete crews poured curb and gutter on River Street along the south half of the project starting at the first driveway approaches north of O’Malley Dr to the River Street dead end cul de sac.
Upcoming Work: Concrete crews will complete the remaining curb and gutter on River Street north of O’Malley Street and all concrete approaches and concrete sidewalk on River Street next week.
Extra Notes: Access to driveways on River Street will be limited for a duration of time to accommodate concrete curb and driveway approach construction including time to allow the concrete to cure. K&R will notify residents affected by this disturbance a prior to concrete construction.