Anticipated Work This Week

  • Storm sewer mainline from STA 40+50 to the north.  Brenner may drop back to cross the 30-inch water main near #832 Kinney.
  • Castings will be raised up to final grade on the GVSU Private Drive.
  • Continue building road up to gravel within the southbound lane of Kinney Ave. to Edinboro.
  • Kent Power will continue installing east side gas services from Edinboro to the north (approximately 12 remaining).  Kent Power anticipates to be completed with all gas main improvements within 1 to 2 weeks.
  • Concrete curb/driveway/sidewalk improvements are scheduled to begin on Thursday, June 6 between the GVSU Private Drive and Edinboro St.

Martin J. Concrete is scheduled to begin installing concrete improvements on Thursday, June 6 and continue into early next week (weather dependent).  After the concrete curb and gutter is poured, driveways and sidewalk through the drive approaches will be installed shortly thereafter.  For all affected residents on within this area, please refrain from driving over the new concrete curb and approaches for 7 days to allow for proper curing.  During this time, you will need to park on the gravel surface of the new road or a nearby side street.  We appreciate your patience during this time while access is temporarily restricted.  Please call Phil Kamp at 616-522-5900 if you have any questions.

This week’s storm sewer installation operation will be concentrated between #860 and #910 Kinney in the northbound lane. Local traffic seeking to travel through this area should expect delays or seek an alternate route.

The base course of asphalt was paved last week at the GVSU Private Drive.