We would like to thank everyone for your cooperation and patience so far as the construction has gotten underway.

Water main work on Lulu Street has been completed and roadway restoration is underway. Paving is tentatively scheduled for next week but will be weather dependent.

Water main work on Pinehurst is progressing well. Water main between West Main and Kenwood has been installed and successfully pressure tested. Bacteriological testing of that segment is underway. The contractor is anticipating working on services in that segment starting next week so residents south of Kenwood should expect a temporary water disruption while services are tied back to the new main. SWT Excavating will be calling those who have a non-copper water service to schedule a replacement date.