Progress Report:
Good progress has been made with testing starting on the first 2,500 ft of water main on Silver Creek this week. Work started at the south end of the project and has progressed north. The crossing of the Mill Pond Culverts was also completed.
Upcoming Work:
The Contractor has decided to pause work for the next few weeks. Work will resume in November on Silver Creek Road.