Progress Report:

After a brief delay due to utility conflicts, pathway construction is back in full swing. This week Kalin Construction will finish building the large block retaining wall, and plan to pave the pathway on Friday. 10/4/2024

Upcoming Work:

Following paving this week, crews will begin the restoration and clean up processes. There will be one more layer of pavement installed, and concrete poured for the access points to the boardwalks and at intersections in the next week.