Progress Report:

The barricades on 48th Avenue are being removed today allowing for through traffic along 48th Avenue. Give ‘Em A Brake Safety will remove all remaining detour signs before Monday, October 28. Thanks to everyone for their patience with construction this fall.

Upcoming Work:

As a reminder, we will continue water transmission main construction after Unity Christian High School is finished with school for the year in late May or early June of 2025. Construction will continue up through Port Sheldon and is scheduled to be completed by mid-August 2025.