Progress Report:
All of the sanitary sewer installation on the project, including lateral services to property lines, has been constructed!
All of the water main on Dixie Drive, including water services to property lines, has been constructed! The water main on Dixie Drive has also passed the pressure and chlorination tests.
Upcoming Work:
Road restoration on Dixie Drive will begin this week and continue over the next couple of weeks.
Water service installation and plumbing work on Mary’s City of David property will continue over the next couple of weeks.