Work completed/in progress:

  • Installed approximately 900 feet of force main.
  • 72nd Ave restored and opened to traffic.
  • Restored farmland east and west of 72nd Ave.
  • Filled force main in preparation for pressure testing.

Anticipated work activities for the coming week:

  • Locate existing utilities near Cleveland Street in preparation for Cleveland Street crossing.
  • Perform pressure test of force main installed to date.