Work completed/in progress:
- Wet well coating began.
- Metal roof completed.
Anticipated work activities for the coming week:
- Continue wet well coating.
- Install soffit, fascia, and vents.
- Pour equipment pads.
- Continue conduit and ductwork installation.
Work completed/in progress:
Anticipated work activities for the coming week: