Work Completed this past week (Aug. 11-16)
- C1, completed sanitary sewer/lateral install on Main Street, North of Dewey.
- C1, road building paused for this week.
- C1, continued storm sewer install on Dewey between Short Street and Main Street.
- C3, dewatering well points installed on Front street from McCoy Creek to Main Street, discharging to McCoy Creek through pre-approved storm outlet.
- C3, continued storm sewer install at Front/Red Bud to Johnson Street.
Work planned for this week (Aug. 18-23)
- C1, continue road building on Red Bud between 3rd and McCoy Creek.
- C1, begin prepping Red Bud for concrete road over culvert.
- C1, begin retaining wall removal at McCoy Creek.
- C1, continue storm sewer install at Dewey/Main Street.
- C1, concrete curb pavement on 3rd Street is planned for Thursday (8/21)
- C3, continue storm sewer install at Front/Red Bud heading west.