Work Completed this past week (Sept 8-12)
- C1, completed sanitary sewer install on 3rs Street.
- C1, completed storm sewer install on 3rd Street.
- C1, placed gravel on Dewey between Main and Red Bud.
- C1, paved base/leveling course on 3rd Street from Skyline Dr. to Red Bud.
- C1, poured footing for retaining wall on Red Bud.
- C3, continued sanitary sewer install on Front St. between Main and Days.
- C3, began installing storm sewer at Front/Days.
- C3, pour curb/gutter from East project limits to McCoy Creek.
- C3, begin installing irrigation at Front/Red Bud.
Work planned for this week (Sept 15-20)
- C1, continue sanitary sewer install on Red Bud North of 3rd Street.
- C1, continue paving driveways/approaches on 3rd Street between Skyline Drive and Red Bud.
- C1, finish pouring retaining wall on Red Bud.
- C3, continue storm sewer on Front Street.
- C3, continue sanitary sewer at Front/Main Street.