Work completed/in progress:
- Wet well, valve chamber, manholes, and gravity sewer installed.
- Valve chamber cored, piping and valve installation started.
Anticipated work activities for the coming week:
- Continue installing lift station equipment.
- Connect to existing force main and test piping.
- Prepare for pouring equipment pads.