Work completed/in progress:

  • Sidewalk, stairs and transformer pad poured.
  • Monorail hoist installed.
  • Electrical equipment, wiring, and lighting installed.
  • Began installation of suction piping, valves, and force mains
  • Cleaned up and graded existing retention pond area.

Anticipated work activities for the coming week:

  • Gravity sewer testing.
  • Force main installation and testing.
  • Generator and transformer installation.
  • Continued mechanical and electrical equipment and wiring installation.