Work Completed this past week (Oct 13 to Oct 18)
- C1, paved base course on Red Bud (South of 3rd), Dewey, and 3rd Street.
- C1, finished pouring remaining curb on Red Bud and Main Street.
- C1, pouring sidewalk on 3rd Street and Red Bud.
- C1, existing street lights (tall concrete ones) removed on Main Street.
- C1, began raising sanitary sewer manholes.
- C3, began sidewalk removals on Front Street/Days.
- C3, poured curb on Front and Days.
- C3, poured concrete road on Front Street.
- C3, continued installing irrigation and street lights.
- C3, poured strain pole foundations at Front/Oak.
- C3, new power poles installed at Front/Oak.
Work planned for this week (Oct 20 to Oct 25)
- C1, paving Red Bud (North of 3rd) and Main Street South of Dewey Wednesday (10/22).
- C1, continue pouring sidewalk on Dewey/Main/3rd/Red Bud.
- C1, continue raising storm/water manholes project wide.
- C3, paving Front/Red Bud on Wednesday (10/22).
- C3, continue pouring sidewalk on Front.
- C3, continue installing street light foundations/conduit on Front Street.
- C3, continue road building/prepping for sidewalk on Front Street and Days.
- Access to Short Street parking lot will remain on Main Street until further notice. Flaggers onsite if access routes need to change during paving.