Work Completed this past week (Oct 20 to Oct 25)
- C1, poured concrete on Main Street and Dewey Street.
- C1, completed mandrel testing/sanitary sewer cleaning on entire USDA system.
- C1, continued raising irons/manholes.
- C3, paved base course on Front/Red Bud up to McCoy Creek.
- C3, continued prepping road/sidewalk.
Work planned for this week (Oct 27 to Oct 31)
- C1, paving Red Bud (North of 3rd) and Main Street South of Dewey Tuesday (10/28).
- C1, continue pouring sidewalk on Dewey/Main/3rd/Red Bud.
- C1, continue raising water main valve boxes project wide.
- C3, paving Front/Red Bud, Main Street, Oak Street on Monday (10/27).
- Access to Short Street parking lot will remain on Main Street, see attached map. Flaggers onsite if access routes need to change during paving.