**Moorland Rd between Heights Ravenna Rd and Wilson Street is closed. This closure will last as force main construction continues.***

** Heights Ravenna intersection is closed and the closure has been extended to Nov 15th **

Work completed/in progress:

  • Completed force main connection north of Crockery Creek.
  • Force Main is installed from Wilson St to north of Heights Ravenna Rd.
  • HMA base course and top course on Moorland Rd between Heights Ravenna Rd and Mt. Garfield Rd have been paved.
  • Moorland Rd is pulverized from Wilson St to Mt. Garfield Rd.

Anticipated work activities for the coming week:

  • Continue grading and shaping Moorland Rd south of Mt. Garfield Rd.
  • Driveway culvert installation to be continued.
  • Start filling force main for hydrostatic testing.
  • Perform hydrostatic test on force main.