Work Completed this past week (Oct 27 – Nov 1)
- C1, poured concrete on Red Bud and 3rd Street.
- C1, poured trench drain
- C1, continued raising irons/manholes.
- C3, finished paving leveling course on Front Street.
- C3, installed strain poles at Front/Oak.
- C3, continued prepping road/sidewalk.
Work planned for this week (Nov 3-8)
- C1, paving top course on all K&R project Tuesday and Wednesday.
- C1, continue pouring sidewalk on Dewey/Main/3rd/Red Bud.
- C1, continue raising water main valve boxes project wide.
- C1/C3, begin installing street lights.
- C3, begin pouring concrete sidewalks Monday – Wednesday.
- Access to Short Street parking lot will remain on Main Street, see attached map. Flaggers onsite if access routes need to change during paving.