Work completed/in progress:

  • Preliminary pump installation
  • Continued installation of valves, piping, and supports
  • Electrical equipment and wiring
  • Force main installed just short of Contract 1 force main

Anticipated work activities for the coming week:

  • Grouting of pump bases and installation of motors
  • Continued piping, valve, and electrical work
  • Diversion Chamber concrete work