Monday, December 15, 2025
- Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
- Last week, K&R installed blowoff piping near the Munn Drain. Pipe laying will continue this week and reach the west side of the 160th Avenue intersection.
- Van Buren Street from US-31 to 128th Avenue is closed.
- K&R continued pipe laying last week, progressing west to east. Pipe laying will continue this week east of 132nd Avenue.
- The contractor will be shutting down the Van Buren jobsites over the holidays. Prior to the showdown, the jobsite will be cleaned up for local traffic. Snow plowing will continue through the holidays.
- Van Buren Street from 104th Avenue to 96th Avenue is closed.
- Ric-Man installed two valve vaults in Van Buren Street. Van Buren Street will be restored and opened to traffic this week.
- New Holland Street from 104th Avenue to 96th Avenue is closed.
- City of Wyoming isolated and drained the existing Transmission Main in New Holland Street.
- Ric-Man will cut into the Transmission Main in New Holland Street and begin pipe replacement.
- Excavation for the surge tank building foundation began. Excavation and densification efforts will continue this week.