Work resumed at the Adrian Pedestrian Tunnel construction site this past week. The project remains on schedule.
Progress Report
- Mass excavation of the site on the west side with a lot of soil removal to get down to the new tunnel and new storm drainage occurred this past week
Upcoming Work Planned for Next Week:
- Old utility poles will be removed
- Additional soil removal and excavation
- Preparation for new drain installation
- No lanes of traffic on M-52 are anticipated to be affected until early March