The snow is melting, which means construction season has arrived! Work on Butler and Catherine are scheduled to begin shortly, the anticipated schedule is below.
Butler Schedule
- Tree removal will begin February 20.
- Water main installation on Butler Street will begin the week of March 3. Work on Butler is expected to take approximately two weeks to complete.
Catherine Schedule
- Tree removal will be completed during the week of February 20.
- Road removal is anticipated to start the week of March 2 with sanitary sewer and water main installation following.
- Catherine Avenue work is anticipated to be complete near the end of July.