- Dry start up of lift station has commenced and will continue over the next several weeks.
- Construction of remaining yard piping commenced last week.
- During pressure testing of station piping, a deficiency with several couplings was discovered. The couplings must be replaced prior to lift station start up.
- The coupling replacement and start up are anticipated to be complete by April 13 pending successful pressure testing and dry startup of other equipment.