Progress Report:
Wednesday was a big day for concrete. The contractor was able to place 11 trucks of concrete to form the base for the aeration detention basins. They will start working on the walls of this structure in the coming weeks.
Upcoming Work:
The walls of the WTP are on hold while we wait for block. This is currently estimated to be delivered in April.